Wednesday 12th October 2016

October site update

 What a month we have had on site!

The tiling is now complete in the first three apartments - even mirrors are up in the bathrooms, cornices are being fitted and the first coats of paint are being applied.

Wardrobes are being fitted and the two lifts are fully operational. Lighting has been fitted in the garage and external rendering is well underway. In fact the scaffolding at the rear of the development should be dismantled imminently.

The kitchens are currently being hand-crafted in the workshop, ready to be fitted in just a matter of weeks, and the floor to ceiling windows are being manufactured for delivery in November.